New construction filling plant RheinRuhr, Plant Family
Concrete construction & civil engineering
Underground construction
Customer | Linde AG |
---|---|
Location | Marl, Germany |
Order value | € 6,340,000 |
Core construction time | 14 months |
Man Hours | About 57,800 |
Project:
- Excavation work
- Canalization / pipeline construction
- Road construction
- Asphalt construction
- Concrete construction
- Reinforced concrete construction
- Technical building installations
- Implementation planning
- 17,900 m³ excavation
- 8,800 m³ concrete
- 200 t reinforcement
- 3,500 m² formwork
- 4,800 m pipeline construction
- 6,300 m cable trenches
- 14,670 m concrete roadway
- 280 t steel construction