New construction of a cleaning area according to WHG and AwSV (Directive on Handling Substances Hazardous to Water)

Traffic area construction
Underground construction
Customer Ruhr Oel GmbH - BP Gelsenkirchen
Location Gelsenkirchen - Horst, Germany
Order value € 5,800,000
Core construction time 13 months

Ausgeführte Leistungen:

  • Excavation work
  • Canalization / pipeline construction
  • Road construction / asphalt construction
  • Trench lining
  • Surface reinforcement according to WHG and AwSV (contamination zone) about 9,500 m²
  • Surface reinforcement in ''normal'' asphalt construction (non-contamination zone) about 1,150 m²
  • 14 cleaning stalls according to WHG and AwSV with a total of about 1,550 m² surface area
  • Rain retention basin HDPE lined with 130 m³ usable volume
  • 3-way seperation system in parallel design 90 l/s with downstream pump station
  • Media supply of the cleaning area via a newly constructed pipeline bridge