New construction of a cleaning area according to WHG and AwSV (Directive on Handling Substances Hazardous to Water)
Traffic area construction
Underground construction
Customer | Ruhr Oel GmbH - BP Gelsenkirchen |
---|---|
Location | Gelsenkirchen - Horst, Germany |
Order value | € 5,800,000 |
Core construction time | 13 months |
Ausgeführte Leistungen:
- Excavation work
- Canalization / pipeline construction
- Road construction / asphalt construction
- Trench lining
- Surface reinforcement according to WHG and AwSV (contamination zone) about 9,500 m²
- Surface reinforcement in ''normal'' asphalt construction (non-contamination zone) about 1,150 m²
- 14 cleaning stalls according to WHG and AwSV with a total of about 1,550 m² surface area
- Rain retention basin HDPE lined with 130 m³ usable volume
- 3-way seperation system in parallel design 90 l/s with downstream pump station
- Media supply of the cleaning area via a newly constructed pipeline bridge