Partially turnkey construction of an industrial plant

Turnkey construction
Concrete construction & civil engineering
Customer Akzo Nobel Chemicals B.V.
Location Delfzijl, Netherlands
Order value € 9,200,000
Core construction time 11 months
Man Hours About 19,000

Ausgeführte Leistungen:

  • Excavation work
  • Canalization / pipeline construction
  • Roads and Asphalt construction
  • Concrete construction
  • Reinforced concrete construction
  • Interior fit-out
  • Creation of non-permeable surfaces
  • Work during ongoing operation

Over the course of one week, a stair tower of site concrete was built to a height of 38 m using a slipform process. The prefabricated stairs were later inserted from the top with a truck-mounted crane and placed on the consoles. At the same time, concrete work was started for the foundation of a high rack storage facility sized 80 by 36 meters.

After the shell of the service building was completed, fit-out started immediatly. Foundation work for pipeline bridges , tank pits and various smaller components was carried out on an ongoing basis. Futhermore, closely coordinated canalization and pipeline construction work was completed, as were all roads and outdoor areas.