Partially turnkey construction of an industrial plant
Turnkey construction
Concrete construction & civil engineering
Customer | Akzo Nobel Chemicals B.V. |
---|---|
Location | Delfzijl, Netherlands |
Order value | € 9,200,000 |
Core construction time | 11 months |
Man Hours | About 19,000 |
Ausgeführte Leistungen:
- Excavation work
- Canalization / pipeline construction
- Roads and Asphalt construction
- Concrete construction
- Reinforced concrete construction
- Interior fit-out
- Creation of non-permeable surfaces
- Work during ongoing operation
Over the course of one week, a stair tower of site concrete was built to a height of 38 m using a slipform process. The prefabricated stairs were later inserted from the top with a truck-mounted crane and placed on the consoles. At the same time, concrete work was started for the foundation of a high rack storage facility sized 80 by 36 meters.
After the shell of the service building was completed, fit-out started immediatly. Foundation work for pipeline bridges , tank pits and various smaller components was carried out on an ongoing basis. Futhermore, closely coordinated canalization and pipeline construction work was completed, as were all roads and outdoor areas.