Turnkey construction of a logistics center
Turnkey construction
Customer | Chocoladefabriken Lindt & Sprüngli GmbH |
---|---|
Location | Aachen, Germany |
Order value | € 7,000,000 |
Core construction time | 9 months |
Man Hours | About 75,000 |
Ausgeführte Leistungen:
- Excavation work
- Canalization / pipeline construction
- Road construction
- Concrete construction
- Reinforced concrete construction
- Interior fit-out
- Work during ongoing operation
- 20,000 m³ excavation
- 8,000 m³
- 950 t reinforcement
- 800 m² formwork
- 4,000 m² facade
- 500 m pipeline construction
- 6,500 m² hall floor slabs
- shipping yard
- 1,100 m reinforced concrete prefab girders
- 5,000 m² reinforced conrete prefab wall slabs