Turnkey construction of a new industrial hall
Turnkey Construction of an Industrial Hall
For our client 3M Deutschland, we delivered the turnkey construction of a modern industrial hall. The project included earthworks, concrete and reinforced‑concrete works, façade works, as well as complete interior construction.
A key focus was the technical building equipment (TGA), which we fully planned and implemented. Equally important was the creation of media‑tight surfaces to meet the highest safety and quality standards.
With around 3,000 m³ of concrete, 250 tonnes of reinforcement, and approximately 3,500 m² of façade surface, we constructed an industrial hall that meets the highest requirements for functionality, safety, and technical performance.
Figures and facts:
- Earthworks
- Concrete works
- Reinforced concrete works
- finishing works
- Drainage systems
- Interior works
- Production of media-tight surfaces
- Work during operation
- Technical building equipment
- Facade works
- Formwork and reinforcement work
The project included:
- 1000 m³ excavated earth
- 2.900 m³ concrete
- 250 t reinforcement
- 2.950m² formwork
- 1.000 m² precast walls
- 180 t steel construction
- 3,300 m² facade
- 400 m pipeline construction
- 2,800 m² WHG storage areas
- 650 m² EX floor coating
| Customer | 3M Germany GmbH |
|---|---|
| Location | Hilden, Germany |
| Contract value | approx. €7 million |
| Main construction period | 12 months |