New construction of a laboratory and a sample storage hall

Turnkey constructionConcrete construction & civil engineeringUnderground constructionPipeline constructionTraffic area constructionIndustrial maintenance

New Construction of a Laboratory and Sample Storage Hall

For our client Sasol, we completed the turnkey construction of a laboratory and sample storage hall. The project included extensive earthworks, concrete and reinforced‑concrete works, as well as the full installation of the technical building equipment.

With more than 5,000 m³ of concrete, 500 tonnes of reinforcement, and a façade area of approximately 3,000 m², we delivered a building that meets the highest standards of functionality and quality.

Figures and facts:

Project: 

  • Earthworks
  • Sewer / pipeline construction
  • Turnkey construction
  • Technical building equipment
  • Civil engineering
  • Concrete construction works
  • Road construction works
  • Asphalt construction
  • Reinforced concrete works

The project included:

  • 2,500 m³ excavated earth
  • 5200 m³ concrete
  • 500 t of reinforcement
  • 18,000 m² of formwork
  • 2,800 m² facade

 

Customer Sasol
Location Brunsbuettel, Germany
Contract value approx. €30 million
Main construction period 40 months
Man hours 180.000
References

Similar references

Neubau Testhalle mit Verwaltungsgebäude in Köln – Schlüsselfertigbauprojekt
Turnkey constructionConcrete construction & civil engineeringUnderground constructionTraffic area constructionPipeline constructionIndustrial maintenance
Neubau Verwaltungs- und Dienstleistungszentrum in Lingen – Schlüsselfertigbau
Turnkey constructionConcrete construction & civil engineeringTraffic area construction
Projects

further references

Efficient technology, perfectly integrated – find out more about our successfully implemented projects.

Learn more