Reference
New construction of a laboratory and a sample storage hall
Turnkey constructionConcrete construction & civil engineeringUnderground constructionPipeline constructionTraffic area constructionIndustrial maintenance
New Construction of a Laboratory and Sample Storage Hall
For our client Sasol, we completed the turnkey construction of a laboratory and sample storage hall. The project included extensive earthworks, concrete and reinforced‑concrete works, as well as the full installation of the technical building equipment.
With more than 5,000 m³ of concrete, 500 tonnes of reinforcement, and a façade area of approximately 3,000 m², we delivered a building that meets the highest standards of functionality and quality.
Figures and facts:
Project:
- Earthworks
- Sewer / pipeline construction
- Turnkey construction
- Technical building equipment
- Civil engineering
- Concrete construction works
- Road construction works
- Asphalt construction
- Reinforced concrete works
The project included:
- 2,500 m³ excavated earth
- 5200 m³ concrete
- 500 t of reinforcement
- 18,000 m² of formwork
- 2,800 m² facade
| Customer | Sasol |
|---|---|
| Location | Brunsbuettel, Germany |
| Contract value | approx. €30 million |
| Main construction period | 40 months |
| Man hours | 180.000 |