New construction of a test hall with administration building and a traversing hall
Construction of a New Test Hall with Office Building and Traversing Hall
For our client NKT, we delivered a turnkey construction project comprising a state‑of‑the‑art test hall, a traversing hall, and an office building. The project included a 2,000 m² industrial floor designed for air‑cushion vehicles as well as a 3,500 m² semi‑rigid pavement serving as a storage area for cable reels weighing up to 150 tonnes.
Technical highlights included the construction of an underground ice storage system for building heating and process cooling, and a concrete rainwater retention basin. In addition, we executed extensive pipeline works up to DN710 and installed the complete technical building equipment.
With this project, we created a facility that meets the highest standards of functionality and precision.
Figures and facts:
- 39.300m³ BRI test and traversing hall
- 2000m² industrial floor for hovercrafts
- 750m² GFA administration building
- 3500m² semi-rigid surface layer as storage area for up to 150t. heavy cable spools
- Construction of an underground ice storage for building heating and process cooling with 8m diameter and 6m height
- Construction of an underground rainwater retention basin in concrete structure
- Laying of 450m PE-HD pipeline up to DN710
| Customer | NKT Holding |
|---|---|
| Location | Cologne, Germany |
| Contract value | approx. €13 million |
| Main construction period | 14 months |