Reference
Semi turnkey Construction of a Gas and Steam Turbine Power Plant
Concrete construction & civil engineeringTraffic area constructionPipeline constructionUnderground construction
Semi‑turnkey Construction of a Gas and Steam Turbine Power Plant
For our client RheinEnergie, we delivered the semi‑turnkey construction of a modern gas and steam turbine power plant. The project comprised extensive earthworks, concrete and reinforced‑concrete works as well as full interior construction. Special requirements — such as complex pipeline and sewer construction, formwork and reinforcement works, and the creation of media‑tight surfaces — were successfully implemented.
In addition, we took on the technical building services, including planning.
Figures and facts:
- Earthworks
- Sewer and pipeline construction
- Road construction works
- Asphalt construction
- Concrete works
- Reinforced‑concrete works
- Interior works
- Construction of media‑tight surfaces
- Excavation works
| Customer | Rhein Energie AG |
|---|---|
| Location | Cologne-Niehl, Germany |
| Contract value | approx. €21 million |
| Main construction period | 22 months |
| Man hours | About 200,000 |