Skip to main navigationSkip to main contentSkip to page footer

We work safe –
or not at all.

Mainka specializes in construction projects in safety-critical industries such as chemicals, energy, and logistics. With clear processes, trained personnel, and a safety culture that is put into practice, our accident rate is a fraction of the average for the construction industry.

Mainka at a glance

Total output 2025

> 330

€ million p.a.

Founded

1895/1949

Branches

8
  • Lingen (head office)
  • Brunsbüttel
  • Gelsenkirchen
  • Cologne
  • Münster
  • Osnabrück
  • Papenburg
  • Wuppertal

Mainka employees

> 750

Accident statistics

Services

Construction projects for chemicals, energy and logistics

We plan, construct, renovate and maintain industrial buildings safely, reliably and with many years of experience. Our focus is on complex projects in sensitive industrial environments such as chemical parks, power stations, refineries, energy infrastructure and large logistics sites.

Reference

Construction of the “Solida 1” Pharmaceutical Production Facility

Construction of the “Solida 1” Pharmaceutical Production Facility in Leverkusen

With “Solida 1”, one of the world’s most modern pharmaceutical production facilities has been built in Leverkusen — and we were able to play a key role from the first idea through to completion.

The project set new standards: a modular building structure, state‑of‑the‑art cleanroom technology, digital infrastructure, and highly automated processes. The demands on precision, hygiene, and safety were exceptionally high — and together with our project partners, we successfully met all of them.

Our scope of work included earthworks, concrete and steel construction, façade works, interior finishing, and the construction of the outdoor facilities. Thanks to clearly defined standards, intensive training, and our strong safety culture, we created an environment in which all project participants could rely on each other at every stage.

Figures and facts:

  • Earthworks
  • Formwork and reinforcement works
  • Work during ongoing operations
  • Roof waterproofing works
  • Concrete construction
  • Road and asphalt works
  • Drainage systems
  • Sewer and pipeline construction
  • Façade works
Customer Bayer AG
Location Leverkusen
Contract value approx. €30 million
Main construction period 35 month

Of our more than 750 employees, around 60% are construction site personnel, whom we train regularly. On average, we devote 2% of annual working hours to training.

order structure

For whom and why?

We generate more than 90% of our turnover in the chemical, energy and specialised logistics sectors. Customers from these sectors trust in our experience because we construct complex industrial buildings reliably and safely.