New construction of a foil factory
Underground construction
Concrete construction & civil engineering
Pipeline construction
Industrial maintenance
Customer | Covestro Germany AG |
---|---|
Location | Dormagen, Germany |
Order value | ca. 26.600.000 € |
Core construction time | 23 months |
Man Hours | ca. 30.000 |
Ausgeführte Leistungen:
- Earthworks
- Sewer / pipeline construction
- Asphalt construction
- Concrete works
- Reinforced concrete works
- finishing works
- Drainage systems
- Interior works
- Work during ongoing operation
- Technical building equipment incl. planning
- Execution work
- Facade work
- Formwork and reinforcement work
- Drainage systems
The project included:
- 17,500 m³ excavated earth
- 6,000 m³ of concrete
- 1,000 t of reinforcement
- 6,000 m² of formwork
- 6,000 m² facade
- 250 m pipeline construction
- 3.000 m² asphalt surfaces